Cat A or Cat B?
Understand the scope.

A practical explanation of office fit-out categories, the gaps to look for and the questions to ask before comparing prices.

Your project checklist ↓
Office fit-out breakout area
Office fit-out breakout area. Photography from the Nexus project archive.

By Nexus Workspace · Reviewed 16 November 2026
For commercial projects in England

Cat A and Cat B describe stages and scope of fit-out, not a simple ladder from cheap to premium.

A practical guide to the decisions, scope and interfaces worth resolving before you commit to the work.

01 / The short answer

A base building is not a finished workplace.

Cat A usually describes the basic internal finish and services provided before an occupier’s layout is fitted out. Cat B is the work that adapts that space to the occupier’s needs. Cat A+ is commonly used for a fitted, ready-to-use offer, but the extent varies.

These labels do not replace a specification. Establish what the landlord is providing, what the tenant must add and what can be reused. The same label can cover different deliverables in different buildings. A modest, practical tenant fit-out can still be Cat B; it does not have to be a luxury interior.

Industry fit-out contractor Overbury explains the distinction between the base provision and occupier-specific work, while noting that the category labels are not standardised definitions. Read the industry explanation.

02 / Compare like for like

What does each category usually mean?

Typical descriptions only. The agreed specification determines the actual scope.
StageWhat it describesWhat to check
Shell and coreThe building structure and base provision before internal fit-out.Which services and common facilities are complete, tested and available?
Cat AA basic internal environment ready for occupier adaptation.Condition, capacities, finishes and service distribution, rather than assuming move-in readiness.
Cat A+A fitted offering intended to reduce occupier setup work.Exact furniture, rooms, connectivity and operational provision included.
Cat BThe occupier-specific layout and fit-out.Who completes every interface with the existing building and client-supplied items?

For an industrial unit, do not assume office fit-out terminology includes a new mezzanine, slab investigations, warehouse services or alterations to the building envelope. List those packages separately.

03 / Your business brief

Start with how people will use it.

Before choosing a finish or accepting a ready-fitted layout, test the space against a typical busy day. Record who is in the building, how they work and what the current layout makes difficult.

  • Occupancy: total staff, peak attendance, visitors and shifts.
  • Activities: concentrated work, video calls, confidential discussions, meetings and collaboration.
  • Facilities: storage, welfare, refreshments, IT equipment and accessible routes.
  • Operations: deliveries, goods movement, security and links with warehouse or production teams.
  • Change: likely growth, flexible rooms and items that can be reused.

A fitted office can be attractive if it matches the brief. If it does not, count the cost and disruption of removing or altering new work. A space needing more initial work may allow a better layout, but the programme and complete cost need to be understood.

04 / Where scope gaps appear

Check the interfaces before signing off.

A partition is not just a wall. It can change light distribution, ventilation, temperature control, detection and the route people take to leave the room. Confirm who coordinates these changes and includes them in the price.

  • Existing heating, cooling and ventilation capacity for the proposed occupancy.
  • Lighting and controls after meeting rooms and private offices are formed.
  • Power and data to actual desk positions, not simply to the floor plate.
  • Door hardware, access control, acoustic privacy and maintenance access.
  • Furniture, AV equipment, network installation and client-supplied items.
  • Testing, commissioning, as-built information and training.

Ask the landlord for available drawings, test records, fit-out requirements and details of any warranties affected by alterations. Agree the condition of existing items before work starts. A service being present is not proof that it is suitable for your proposed use.

05 / Cost & programme

Compare the work, not the category.

There is no meaningful universal Cat A or Cat B price for an undefined project. Area, existing condition, specification, services capacity, occupancy during works and procurement all affect the budget. Ask each bidder to price the same drawing revision and identify exclusions and allowances.

  • Separate the landlord’s work, contractor’s work and your own purchases.
  • Include surveys, design, approvals, furniture, IT and relocation where relevant.
  • State the VAT basis, provisional sums and how changes will be priced.
  • Ask for key dates: design decisions, approvals, procurement, site works and commissioning.
  • Record the dependencies behind the proposed occupation date.

Discuss lease obligations and reinstatement requirements with your property adviser. A lower initial build cost can be misleading if it creates avoidable alteration or end-of-lease work later.

06 / A usable result

Keep responsibilities clear through handover.

Check the consent and approval route for the actual works. Building Regulations approval and planning permission are separate; an existing office use does not settle every alteration. GOV.UK explains when to check approval.

Agree who is managing design, construction, building interfaces and client-supplied works. Commercial client duties remain relevant regardless of whether the project is called Cat A or Cat B. Read HSE’s client guidance.

At handover, check the completed rooms against the agreed scope and collect the required commissioning, testing and completion records. Record snags, owners and dates. Include operating instructions, maintenance contacts and training so the team can use the space properly from day one.

Keep something useful

Before you request a quotation

Copy these prompts into your project brief. Record anything unknown, who will check it and when the answer is needed.

  • Landlord’s specification and condition records obtained.
  • The actual included scope listed, beyond the Cat A, A+ or B label.
  • Occupancy, activities and room requirements confirmed.
  • Existing services checked against the new layout.
  • Contractor, landlord and client-supplied work allocated.
  • Like-for-like quotation, exclusions and provisional allowances reviewed.
  • Consent, programme, handover and lease-related questions assigned.

Take the next step

Turn the brief into a workable plan.

Our fit-out design guide includes a free editable planning workbook, with briefing, quotation comparison and handover prompts.

Open the planning workbook ↗

Common questions

A few useful answers

Is Cat B always more luxurious than Cat A?

No. Cat B describes fitting the office to the occupier’s requirements. It can be straightforward and functional or highly bespoke.

Does Cat A mean we can move straight in?

Not necessarily. Check what is included and what still needs to be added for your staff, equipment and layout.

Is a mezzanine included in Cat A?

Do not assume it is. A new mezzanine is a separate structural package that must be explicitly included in the scope.

Should we choose a fitted office or fit out our own?

Compare both against the same operational brief, lease terms, complete budget and occupation date. The better option is the one that meets the business need, not the one with the more impressive label.