Call today for a free quote & site survey
Project Updates

Office Mezzanine Floor – Nifty Lift Project Update

By September 10, 2019 No Comments

OFFICE MEZZANINE FLOOR NIFTY LIFT PROJECT UPDATE

We are implementing an office mezzanine floor project for one of the largest manufacturers of mobile elevating work platforms in Europe.

Nifty Lift

WHAT'S INVOLVED

We are implementing an office mezzanine floor project for one of Europe’s largest manufacturer of mobile elevating work platforms (otherwise known as cherry pickers). Nifty Lift require additional office facilities for their research and development team working within their 9000 square metre warehouse in Milton Keynes.

The 270 square metre mezzanine floor project will involve the creation of a large open plan office space, two meeting rooms, a 3D printing room and a kitchen space. The mezzanine steels are also being left exposed on this project as they have a dual purpose. They’re being used to hang the cranes for their manufacturing facility too.

The 17 metre span steels used in this project, are the largest that we have designed and installed to date. The building was initially built to accommodate an additional floor but it was never built. So we have taken advantage of that in our design and bolted our mezzanine steels onto their existing facilities. The full turnkey project will take 16 weeks from start to finish and it includes the installation of all partitioning, ceilings, electrics, plumbing and air conditioning.

WEEK
ONE

First things first, we need to set up site in correspondence with CDM regulations to ensure the health and safety of Nifty Lift’s employees and our installation team during the project.

Next up the mezzanine floor get’s delivered to site and we carefully manoeuvre the steels into the warehouse before getting to work erecting them. The mezzanine steels take a weekend to build and attach to their existing facilities. As the mezzanine steels are to be left exposed on this project, we need to paint the steels with intumescent paint instead of installing a fascia to protect them in the event of a fire.

Nifty Lift Pre Mezzanine
Nifty Lift Delivery
Nifty Lift Mezzanine Build
Mezzanine Build For Nifty Lift
Nifty Lift Mezzanine Install
Mezzanine Fire Rating
Fire Retardant Paint On Mezzanine
Mezzanine Being Painted

Heading into week two once the main beams have been erected and the intumescent paint has been applied, it’s time to start installing the first floor high level perimeter wall cladding.

This stage of the project is split into two parts which totals five weeks for both the ground and first floor combined. We’re starting with the first floor cladding so that we have access on the ground floor to install the purlins and decking at a later date.

WEEK
TWO-
FIVE

Nifty Lift Cladding
Cladding Going Up At Nifty Lifts
Nifty Lift Cladding Installation
Office Mezzanine Build For Nifty Lifts
Nifty Lift Week Three
Nifty Lift Cladding Week Three
Cladding In Week Three Nifty Lift
Nifty Lift Office Mezzanine Build Week Three

WEEK
SIX

Heading into week six and with the perimeter boards now installed creating the outline of the new facilities, we make a start on installing the floorboards on top of the mezzanine floor. First we erect the netting underneath the mezzanine floor to ensure a safe installation and then make a start on installing the mezzanine decking. The new 270 square metre office space will be home to Nifty Lifts new open plan office, complete with two meeting rooms, a 3d printing room and a kitchen.

Nifty Lift Week Six Of The Build
On Site At Nifty Lifts
Mezzanine Decking Complete
Office Mezzanine Project at Nifty Lifts
Office Mezzanine Decking Nifty Lifts
Mezzanine Build For Nifty Lifts
Mezzanine Decking Installation
Nifty Lift Office Mezzanine Build

PROJECT UPDATE VIDEO

The mezzanine is up, the perimeter walls have been installed and the floorboards are down, so we paid a visit to site to produce a video update in the project’s sixth week.

As the project enters it’s seventh week, it’s time to make a start on building the new office facilities on top of the mezzanine floor. The office space is to be created through the installation of a mixture of solid and glass partitioning.

Our installation team marks out the partition runs and once they are fixed to the floor, the vertical posts and head tracks are installed section by section, creating the structure to attach the plasterboards to. The plasterboards are then cut to size and fixed to the stud to create the walls of the new office space.

Heading into week eight and the tape and jointing is carried out on the new partitions. This process involves the reinforcing and covering of the seams between the sheets of the plasterboard. Essentially, joint tape is applied to the seams and then is covered with a jointing compound and smoothed over to create a seamless finish. This then prepares the new walls for decoration. We are also creating the enclosure for the staircase that will grant access to the mezzanine.

WEEK
SEVEN-
EIGHT

Nifty Lifts Office Construction
Office Mezzanine Build For Nifty Lifts
Nifty Lifts Office Build
Nifty Lifts Partitioning Construction
Tape and jointed office partitioning
Walls tape jointed at Nifty Lift
Office Partition Build for Nifty Lift
Staircase Enclosure Build

WEEK
NINE-
TEN

During week nine we finish off the cut-outs for the doors and windows and install the aluminium glass frames in preparation for the glazing to go in at a later date. The rest of week nine involves the decoration of the new partition walls. As the project enters it’s tenth week, we make a start on installing the suspended ceiling grid and the tiles, with some ceiling areas due to be completed this week, such as the new hallway area. We are also creating light tunnels within the open plan office to allow natural light in, so the outline of these are also created within the ceiling grid.

Aluminium Glass Frames Installed On Site
Ceiling Grid Installation
Ceiling Tiles Being Installed
Staircase Construction Nifty Lift

The project is nearing completion as we head into the eleventh and twelfth week. The new window glazing frames and the glazing itself is installed in the eleventh week, whilst the decoration is completed throughout with the emulsion applied to all the new partitions and we prime, undercoat and gloss the skirting, window and door frames.

The suspended ceiling installation is completed both above and below the mezzanine floor and the lighting is installed throughout. We enter week twelve and the new power outlets, the floor boxes and back boxes that were required both above and below the mezzanine are completed. The last of the works to complete that week are the plumbing and HVAC systems for the new facilities.

WEEK
ELEVEN-
TWELVE

Nifty Lift Staircase Enclosure
Nifty Lift Staircase
New Office Facilities Nifty Lift
Nifty Lift Ceilings
Kitchen Nifty Lift
Nifty Lift Mezzanine Windows
Staircase At Nifty
Staircase Construction Nifty Lift

MORE
TO
COME

This is where we’re up to so far on the project, but keep checking back each week to see more pictures, videos and updates on where we are up to with the build.

If your business is on the move or you are looking to create more office, storage or production space within your warehouse, we can help. We specialise in helping businesses to make the most of their space through the design and installation of mezzanine floor solutions.

HOW WE
CREATE
YOUR
MEZZANINE

Our specialist mezzanine process.
Your mezzanine project needs a dedicated team of expert designers, installers and project managers to implement. Our comprehensive process Nexsteps™ guides you through every step of the way.

WHERE WE WORK

We would love to be able to help create workspaces for businesses throughout the whole of the UK but unfortunately we can’t. The extra cost to you and the fact that we wouldn’t be able to manage your project to our high standards means that we must set a limit for how far we can work. The area we cover is highlighted to the right. As you can see, we essentially work as far North as Newcastle and as far South as Birmingham. So if your business is situated in an area we cover, get in touch today to discuss your plans for your new workspace.

GET A QUOTE
Nexus Where We Work

RELATED POSTS

Nifty Lift Mezzanine Install
Project Updates

Office Mezzanine Floor – Nifty Lift Project Update

JTNDaDElM0UlMEElM0NzcGFuJTIwc3R5bGUlM0QlMjdjb2xvciUzQSUyM2ZmZmZmZiUyNyUzRU9GRklDRSUyME1FWlpBTklORSUyMEZMT09SJTNDJTJGc3BhbiUzRSUwQSUzQ3NwYW4lMjBzdHlsZSUzRCUyN2NvbG9yJTNBJTIzZTliOGNmJTI3JTNFTklGVFklMjBMSUZUJTNDJTJGc3BhbiUzRSUwQSUzQ3NwYW4lMjBzdHlsZSUzRCUyN2NvbG9yJTNBJTIzZmZmZmZmJTI3JTNFUFJPSkVDVCUyMFVQREFURSUzQyUyRnNwYW4lM0UlMEElM0MlMkZoMSUzRQ== We are implementing an office mezzanine floor project for one of Europe's largest manufacturer…
Zak Lewis
September 10, 2019
Birstall Victoria vs Dewsbury Moor
Project Updates

Birstall Victoria Sponsorship

JTNDaDElMjBzdHlsZSUzRCUyN2ZvbnQtc2l6ZSUzQTYwcHglMjAlMjFpbXBvcnRhbnQlM0IlMjBjb2xvciUzQSUyMzAyMDA0YiUyMCUyMWltcG9ydGFudCUzQiUyMGxpbmUtaGVpZ2h0JTNBNjBweCUyMCUyMWltcG9ydGFudCUyNyUzRUJJUlNUQUxMJTIwVklDVE9SSUElMjBTUE9OU09SU0hJUCUyMEFOTk9VTkNFTUVOVCUzQyUyRmgxJTNF We are delighted to announce that we are sponsoring Birstall Victoria ARLFC under 12’s…
Zak Lewis
July 17, 2019
Zak Lewis

Author Zak Lewis

More posts by Zak Lewis

Leave a Reply