Skip to main content

Project archive · Wakefield · February 2020

Room to make.
Space to grow.

A two-tier mezzanine project for Green & Brown, creating additional production accommodation above retained ground-floor storage.

Discuss your production space
Green and Brown employees using the completed mezzanine production space
The new production accommodation in use, from the original project record.

01 · The brief

More production within the existing warehouse.

Green & Brown manufactures handmade interior furnishings, including blinds and curtains. At the time of this project, the business needed additional production space at its Wakefield premises to accommodate demand.

The design-and-build brief replaced an area of high-bay racking with a two-tier mezzanine. Production accommodation occupied the new levels, while storage remained at ground level. The scope also included fire protection, lighting and electrical work.

This historical account was originally published on 18 February 2020. Its fourteen-week programme and construction details describe this particular project, not a standard design or delivery timescale.

02 · Fourteen weeks on site

From enabling works to a working facility.

Weeks one and two · Preparing the support

The existing high-bay racking was dismantled and set aside for later reuse. Project-specific foundation work followed: the original diary records cutting through the slab, installing driven piles and forming the support arrangement for the proposed loads.

That foundation solution belonged to this building and design. It should not be treated as a recommendation for another warehouse without an engineering assessment.

Weeks three to six · Building the frame

Steelwork arrived and the team installed the columns, beams and purlins. The new mezzanine levels were coordinated with Green & Brown's existing floors, including the level adjustments described in the original construction record.

Weeks seven to nine · Decking and enclosure

The project diary records temporary protection, purlin links and deck installation, followed by perimeter panels fitted to the shape of the roof. Electrical first-fix work began at the upper level and the second-floor pallet gate was installed.

Weeks ten to twelve · Protection and services

Column cases, perimeter fascia and suspended ceilings formed part of the specified fire-protection work. Perimeter walls and electrical installations progressed across the levels as the team completed the accommodation around the frame.

Weeks thirteen and fourteen · Fitting out for use

The remaining electrical work and shelving were completed. Existing ground-floor pallet racking was replaced with the new arrangement, allowing the facility to be handed over. The original photographs show Green & Brown's team using the new production space.

03 · The project record

Follow the transformation.

The original update included three videos: the construction time-lapse, a project progression film and a discussion with Job Brown, then identified as Head of Operations and IT.

The original construction and completed-project photographs are retained in sequence in the gallery below.

Planning your own industrial mezzanine floor? Start with the intended production loads and our warehouse slab guide. HSE explains the commercial client's duties for a new construction project.

Planning production space

Start with the operation, not just the floor.

Tell Nexus Workspace what you need to make, store and move, and what must continue while the building changes. We can help define the next steps for your site.

Talk about your project
Zak Lewis

Author Zak Lewis

More posts by Zak Lewis

Leave a Reply